Last Day List: Critical Cutover Information for Leaders

8/20 Update to HR Core: Deleted Move worker to another manager/supervisory org.

8/4 Update to Supply Chain: Capital, Service, and Bill Only POs freeze on 9/16; Goods & Inventory POs (aka Non-Stock & Stock POs) will freeze on 9/23

6/24 Update to Finance: Dates and wording updated to July 1 – Mid Nov. No new cost centers, cost center name changes, cost center hierarchy changes, or reorganizations.

6/19 Update to Core HR: First date in the new system for Sup Org changes (including re-organizations) was updated to mid-November.

See 6/5 Updates to Learning

See 6/4 Updates to Benefits and Payroll


Our UKG go-live is September 21, with the Workday and the expanded Employee Center go-live set for October 1. However, HR, Finance, Supply Chain and TSG have months of preparation activities to complete in advance.

For your convenience, we have provided critical dates that support the cut-over process. Unless otherwise noted, departments will not be able to perform the tasks between the last day in the current system and the first day in the new system.

What Does This Mean for You?

Plan ahead. Do as much as possible before the Last Days shown below.

Do not request the activities below between the Last Day and First Day. Please respect these dates. Making changes to our current systems during the freeze dates interrupts the teams’ ability to perform final data conversion and set-up of the new systems. It puts patient care, the go-live date and possibly on-time payroll at risk.

Do not print this list. Use this as the one location for this information, so that you have all additions and updates. We encourage you to check back to ensure you have the most current information.


Human Capital Management

Last Day in Legacy

First Day in Workday

Activity

Notes

Benefits

   
Sept. 12Oct. 1New hire benefit eventsNew hires starting on Aug. 25 and Sept. 8 encouraged to enter benefit elections by Sept. 12
Sept. 12Oct. 1Change benefits for life/qualifying event 
Sept. 12Oct. 1Change beneficiary 
Sept. 12Oct. 1Change to Dependent Care/Healthcare FSA 
Sept. 12Oct. 1Change/drop dependent event 
Sept. 12 UPDATED 6/4Oct. 1Submit licensure/certification reimbursement request 
Sept. 12 
UPDATED 6/4
Oct. 1Submit licensure/certification bonus request 
Sept. 12
UPDATED 6/4
Oct. 1Submit Tuition Reimbursement/Tuition Assistance requests 
Sept. 12
UPDATED 6/4
Oct. 1Submit Childcare Subsidy amounts 
Sept. 13Oct. 1Update leave status 
Sept. 19Oct. 1Updates to pension 
Sept. 19Oct. 1Change retirement savings 
    

Compensation

   
July 27Oct. 1Request compensation change - special adjustments 
July 27Oct. 1Request new/changes to pay premiums outside of hiring eventWeekend, Resource Pool, Flex
July 27Oct. 1Process market adjustments 
July 27Oct. 1Create net new compensation grades 
July 27Oct. 1Change 12-digit position codeIncludes: grade changes, remapping employees to different job code, exemption status changes on job, shift code
Feb. 17 Oct. 1Create new/change job profiles (4-digit job code)Part of the Workday configuration freeze that was effective Feb. 17 (freeze already in place)
Sept. 1Oct. 1Request compensation change - education relatedProcessed quarterly
Sept. 13Oct. 1Request compensation change – allowances/recurring paymentsInterim pay, mobile phone allowance, commuter allowance, etc.
Sept. 13Oct. 1Request/process one-time paymentsBonuses, stipends, non-recurring repayments, etc.
    

Core HR

   
July 1mid-Nov.
UPDATED 6/19
No new/changes to Supervisor Organization structures/relationships including reorganizations 
July 27Oct. 1Changes to UKG/Kronos codes and shift codes (ad hoc) 
Sept. 8Oct. 6External hiresNo hires starting Organization/System Orientation on Sept. 22
Sept. 12Oct. 1Change contact/personal information (name changes, emergency contact, address, marital status, etc.) 
Sept. 13Oct. 1Adding/changing additional jobs (secondary positions, etc.) 
Sept. 13Oct. 1Changes to status (FT, PT, etc.) and FTE value 
Sept. 13Oct. 1Separate/terminate employeesAllow pending separations but not process during catch-up period. Process on Sept. 30 and catch up in Workday.
Sept. 13Oct. 1Vaccines and workplace testsEmployees who submit vaccines and workplace tests up until Sept. 28 will be entered into Workday during the Sept. 29 - 30 hard freeze/quiet period.
    

Learning

   
Sept. 15Nov. 3Assign or enroll in education

UPDATED: 6/5

Any assigned training must be completed by Nov. 3.

Required training not completed in Cornerstone by Nov. 3 will be re-assigned in Workday for completion. All progress made in Cornerstone will be lost.

Sept. 15Oct. 15Enrollments in RQI, NRP, or Non-Violent Crisis Intervention elearning modules

UPDATED: 6/5

RQI, NRP and Non-Violent Crisis Intervention elearning modules assigned in Cornerstone on and after July 1, must be completed in Cornerstone by September 15.

Past due modules will result in expired AHA or NRP certifications.

NVCI elearning module progress will be lost and may result in an expired NVCI certification.

Employees will receive their RQI, NRP, and Non-Violent Crisis Intervention elearning modules in Workday Learning on October 15

Sept. 15 Annual skills checklists

UPDATED 6/2

This applies to annual skills checklists in Cornerstone and annual skills validations assigned in Elsevier Clinical Skills

Sept. 15 Cornerstone checklists

UPDATED 6/2

No new checklists will be assigned in Cornerstone

Nov. 3Oct. 1Orientation/required trainingAny orientation or required training assigned in Cornerstone will be completed.
N/AAfter Nov. 1Elsevier Clinical Skills

ADDED 6/2

All Checklists and Clinical Skills will be assigned in Elsevier Clinical Skills

    

Payroll

   
Sept. 12
ADDED 6/4
Oct. 1PayrollW4 tax withholdings
Sept. 12
ADDED 6/4
Oct. 1PayrollDirect deposit setup/ changes
    

Recruiting

   
Sept. 13Oct. 1New job requisitions approved (new or replacement) 
Sept. 13Oct. 1Change/close job requisitions 
Sept. 13Oct. 1Close/change evergreen requisitions 
Sept. 13Oct. 1Internal job changesLateral transfers, upgrades, promotions, demotions.
Sept. 28Oct. 1Job applications—internal and externalApplicants who apply in SAP (and are not in offer stage) up until 9/28 will be entered into Workday during 9/29-9/30 hard freeze/quiet period.
Sept. 28Oct. 1Offers to candidatesOffers made in SAP prior to 9/28 will be completed in SAP and direct hired into Workday. Verbal offers made after 9/29 will be caught-up in Workday.
Sept. 28Oct. 1Post job statusFilled postings will be taken down by Recruiters during catch-up period and updated in Workday.
    

Talent

   
OngoingOct. 1Disciplinary actionsDA’s completed after 9/14 will not be processed in Lawson and will be entered into Workday after go-live.
OngoingOct. 1Performance improvement discussions 
OngoingOct. 1Development plans 
Sept. 13Oct. 1New/changes to certifications in Cornerstone 
Sept. 13Oct. 1New/changes to education/degrees in Cornerstone and Lawson 
Sept. 13Oct. 1New/changes to clinical licensures in LawsonClinical licensure changes after 9/14 will not be processed in Lawson and will be entered into Workday after go-live.
Sept. 13Oct. 1End-of-orientation reviews 
Sept. 28Oct. 1Providing feedback 
    

Supply Chain Management

Last Day in Legacy

First Day in Workday

Activity

Notes

July 21Oct. 1Supplier Soft FreezeSoft freeze means we are dual entering data in Lawson and Workday, no change in customer behavior
July 21Oct. 1Purchase Item Soft FreezeSoft freeze means we are dual entering data in Lawson and Workday, no change in customer behavior
Aug. 4Oct. 1Supplier Hard FreezeHard freeze means we are no longer creating the data in Lawson unless it is an emergency, but we are creating that data in Workday for Oct. 1
Aug. 4Oct. 1Inventory Site Hard FreezeHard freeze means we are no longer creating the data in Lawson unless it is an emergency, but we are creating that data in Workday for Oct. 1
Aug. 4Oct. 1PAR Area Freeze 
Aug. 21Oct. 1Purchase Item Hard FreezeHard freeze means we are no longer creating the data in Lawson unless it is an emergency, but we are creating that data in Workday for Oct. 1
Sept. 1Oct. 1Sourcing & ContractingAll sourcing and contracting activities will no longer be put into Lawson, but contract processing and signatures will continue as usual and be loaded to WD after Oct. 1
Sept. 12Oct. 1Last Requisition DateAny urgent needs will need to be manually processed without the ERP, you will still accomplish this via Jira Service Desk - but only high priority marked tickets will be processed
Sept. 16Oct. 1Capital, Service, and Bill Only POs freeze. UPDATED 8/4Any urgent needs will still be ordered with a manual PO #, tracked manually in spreadsheets for load to WD on Oct. 1, and with the buyers calling in orders to suppliers - with nothing entered into Lawson
Sept. 23Oct. 1Goods & Inventory POs (aka Non-Stock & Stock POs) will freeze UPDATED 8/4 
Sept. 25 UPDATED 6/2Oct. 1Last Receipt DateAny goods received after this date will be manually tracked in a spreadsheet for receipt for load to WD on Oct. 1, but nothing will be put into Lawson
Sept. 25 UPDATED 6/2Oct. 1Last Inventory Issue DateAny urgent inventory issued out of the warehouse after this date will need to be tracked manually in a spreadsheet for load to WD on Oct. 1, but nothing will be put into Lawson
Sept. 25 UPDATED 6/2Oct. 1Last Invoice Entry DateNo invoices will be paid from this date until after they are loaded in WD on Oct. 1. Every invoice from before this date will be paid before Oct. 1. Suppliers should see no delay in our ability to meet payment terms
    

Finance

Last Day in Legacy

First Day in Workday

Activity

Notes

July 1mid-Nov.No new cost centers, cost center name changes, cost center hierarchy changes, or reorganizations DATES and ACTIVITY UPDATES 6/24 
Aug. 1Oct. 1No new requests for activities 
Aug. 1Oct. 1No changes to Epic charge/adjustment codes 
Sept.17Oct. 1All invoices and liabilities due for inclusion in Year End financials, including Nexus go-live and Crystal Springs Tower expensesThis is a shift from typical dates

UKG Timecards and Schedules

Last Day in Legacy UKG Workforce Central

First Day in UKG Pro Workforce Management

Activity

Notes

Scheduling

   
N/AAug. 17Soft Go Live (Scheduling only)Production available for schedulers only
N/AAug. 18 - Sept. 19Basic Scheduling Labs—Basic Schedulers attend to verify information and enter schedules and PTO requests in preparation for go-liveManagers need to determine the last day for the entering of PTO in WFC (consider Aug. 18 – Sept. 21)
N/AAug. 18 - Sept. 19Advance Scheduling Labs—ADVS Schedulers attend to verify information, enter the last two weeks of current schedule (Sept. 21 – Oct. 4), and enter PTO in preparation for go-liveSchedulers will need to go back in and finish after schedule sign up closes. Managers need to determine the last day for the entering of PTO in WFC (consider Aug. 18 – Sept. 21)
Aug. 26 - Sept. 9N/ASchedule sign upEmployees select their shifts for Oct. 5 - Nov. 1
Sept. 16N/ALast time TSG posts the scheduleFor period of Oct. 5 - Nov. 1
Sept. 21Sept. 21Go-liveUKG Pro Workforce Management is available to everyone. ADVS employees can see the remaining two weeks of the current schedule and the whole next scheduleNear go-live you will be notified of the time of cutover. 
Sept. 21Sept. 23 - Oct. 7Schedule sign up Employees select their shifts for period of Nov. 2 – Dec. 13
N/AOct. 21First time managers post the scheduleManagers balance and post schedule for period of Nov. 2 – Dec. 13

Timekeeping

   
Sept. 20Sept. 21PunchingUKG Pro Workforce Management is available to everyone.Near go-live you will be notified of the time of cutover. There will be some employees who clock-in in one system and out in the other. UKG Administrators will migrate punches for managers and timekeepers
Sept. 20Oct. 6Payroll close (Kronos Mondays)Timekeepers go into WFC verify and approve timecards
Sept. 26Oct. 10Paychecks 

 